BILGE LINE

The work of this contract is to collect bilge and oily residues from ships (tankers) docked on the Oil Jetty No 1 & No 2 Berths Western Oil Jetty, with a future connection provided for EOJ shipping with valve and blank flange. The Pipe Line is 3” Carbon Steel, API 5L Grade B, Seamless, Schedule 40, Shot Blasted and primed to SA2.5. When a ship is berthed on the WOJ it will connect to the on shore connection located beside the existing Lagan line with a certified hose reel. A sludge removal company will connect to the connection point adjacent to Berth 40 see drawing for exact location with a hose. The waste will be removed from the ship using their own pump on the ship and it will be pumped into a road tanker for disposal by a certified waste sludge company. Once the required waste is removed from ship (tanker) the appropriate connection / fittings can be disconnected